Design of the rehabilitation / reconstruction of Lake Ridge Road (Regional Road 23) from Myrtle Road (Regional Road 5) to 1.6 kilometres north of Chalk Lake Road is ongoing. Work includes road resurfacing, partial paved shoulders and culvert replacements. Regional Contract D2022-47.
The Region’s contractor, Green Infrastructure Partners Inc. (GIP Inc.) will be remobilizing the week of April 17, 2023, to complete the remaining work by September 2023.
Residents should expect minor traffic delays and are asked to exercise additional caution for the safety of the construction workers. Access to residential driveways will be maintained whenever possible. Notification will be given to residents if vehicles need to be moved out of their driveways.
Questions: Should you have any questions or comments, please contact
the following staff member from the Regional Municipality of Durham Works Department.
Robert Baldasaro
Project Supervisor
905-668-7711 or 1-800-372-1102 extension 6521
robert.baldasaro@durham.ca